Huang Guojun, Jiang Dingshen. Designed flood standard for the construction of check dam in loess area[J]. Bulletin of Soiland Water Conservation, 1988, 7(2): 52-56.
DOI:
Huang Guojun, Jiang Dingshen. Designed flood standard for the construction of check dam in loess area[J]. Bulletin of Soiland Water Conservation, 1988, 7(2): 52-56.DOI:
Designed flood standard for the construction of check dam in loess area
At present the chech dam for building farmland constructed in loessarea
generally
is designed and checked according to the oppotunity of onetime in 10 year and one time in 30 years respectively
which has been dem-onstrated in practice to be lower and thought as the major reason to causedam bursting.Having been studied
the optimum designed standard of floodis one time in 20 years and one time in 50 to 100 years for designed floodand flood check respectively.On total consumption of money and material
it will save 15-20% of that
compared with the two adjucent standard ofdesigned flood.It is suggested that the major engines of the check dam bedesigned on the standard of one time in 25 years